久久免费视频播放|色戒西瓜影音电影完整版|孤儿怨未删减完整版在线观看樱花影视|香港战役电影完整版在线看未删减,国产小视频你懂的,亚洲第一页在线观看,黄视频网站在线看

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Weather conditions are identified as critical risks for an offshore wind park development project. To mitigate risks associated with bad weather conditions, the project manager creates a contingency plan to and more time to the planned schedule. At the time of execution a hurricane comes close to the wind park area so that all activities need to be stopped immediately.What should the project manager next?
A、Update the risk register and create a change request.
B、Get additional approval from the steering committee.
C、Change the schedule of the team members accordingly
D、Avoid any chances to keen the project management plan as if was approved.


相關(guān)試題

推薦文章