試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A newly hired project manager is assigned three projects to close. The projects have been completed and a final review is to be performed. The project manager discovers that none of the five phase reviews were performed to have a go/no go decision.What should be done?
A、Identify all completed documents and declare the projects closed.
B、Call a meeting of stakeholders of each project to plan phase reviews that were missed
C、Confirm documents validating completion and acceptance of deliverable for each phase document lessons learned conduct a final review of it all and archive the project documents
D、Closing of these project does add any value and is a waste of time that can be applied to other projects