試卷名稱 2017年信息系統項目管理師最新英語模擬題(2)
考試中心《2017年信息系統項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The project manager is completing the project the final product is finished, all defects found to date are corrected and the product is delivered to the client. The project manager announces the end of project. A week later the client contacts the project manager because they found a defect and they want to project manager to repair it. The client claims that the project is not yet closed because they are still testing the product. How does the project manager respond to this situation?
A、Tell the client that the project is finished and there will be no repairs to the defect because warranty period was not defined in the contract.
B、correct the defect and tell the client it’s the final repair to defects
C、correct the defect and get formal accept from client
D、Ask the client to send a change request to change the project scope statement