試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A two-year project is 50% complete has a schedule performance index of 1.051and a cost performance index of 1.02, A new project enters the portfolio and is deemed a higher priority than the current project. As a result, the current project loses three key resources, Despite tossing resources, the project manager is asked by senior management to complete the project on time and within budget without additional resources.
A、executive resources balance
B、crashing
C、change the project baseline
D、implement deviation analysis