試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A customer initiates a new strategic project, Which must be completed by the end of the year. The project is critical to the strategic success of the customer. An idea about the scope, budget, and timeline has already been discussed.What else should be included in the project charter?
A、Approved budget, named resources, and fixed-end date
B、Quantified risks, limits and exclusions, and revised milestone dates
C、High-level requirements, high-level risks, and identified scope
D、Project plan, scope plan, and resource plan